top of page
Microsoft Building– Pyramids Smart Village
واجهات مبني مايكروسوفت بالقرية الذكية - مصر

The project consists of Cable Supported Steel Curtains are arranged over the façades of the glass facades of the building (A) at the Smart Village. At each façade, three louvers of a length 33 m were suspended from 2 stainless steel cables anchored at its upper end into an upper space truss roof and into a r/c structure at its lower end. A design concept, full design, workshop drawings and site supervision were carried out. This design combines the technical innovation with the elegance in form. For the whole supporting structure and for the construction joints, e.g. cables anchorage at their ends, steel clamps between cables and steel structure. An erection concept and program was introduced which was completely followed under our full supervision.

Owner: Smart Village Company

Contractor: GENZA Company

Date: 2000 – 2001

bottom of page